ACC 112 - HB 127 Financial Report FYE 2022 |
|
---|
Personnel Services Costs | $1,375,319.84 |
Operating Expenditures | $358,032.62 |
Personnel Services Costs & Operating Expenditures Total | $1,733,352.46 |
Number of Personnel | 16 |
Permit Revenues | $1,145,194.26 |
HB 127 Summary Start: 10/1/2021 to End: 9/30/2022 |
|
---|
2A - Apply Date |
|
Permit Applications Count: | 4807 |
2B - Issue Date |
|
Permits Issued Count: | 4353 |
2C - Request Date |
|
(Re)Inspection Request Count | 16934 |
2D - Actual End Date |
|
(Re)Inspection Done Count: | 16210 |
2E - Actual End Date
|
|
Private Provider (Re)Inspection Done Count: | 230 |
2F - Actual End Date
|
|
Audit (Re)Inspection Done Count: | 38 |
HB127 for BD Start: 10/1/2021 to End: 9/30/2022
2A-Apply Date | Permit Number | Abandoned | Denied | Expired | Fees Due |
| Finaled | In Review | Issued | On Hold | Submitted |
| Void | Total |
| Permit Applications Count: | 7 | 5 | 634 | 28 |
| 2547 | 134 | 1003 | 50 | 98 |
| 303 | 4807 |
2B-Issue Date | Permit Number | Abandoned |
| Expired | Fees Due | Finaled | In Review | Issued | On Hold | Void | Total |
| Permits Issued Count: | 1 |
| 687 | 4 | 2699 | 3 | 938 | 2 | 19 | 4353 |
2C-Request Date | Inspection Number | Cancelled | Completed | Partial Pass | Passed | Pending | Re-inspection Required | Re-inspection Required (with fee) | Requested |
| Total |
| (Re)Inspection Request Count: | 455 | 5809 | 1425 | 5643 | 3 | 2792 | 22 | 784 |
| 16934 |
2D-Actual End Date | Inspection Number | Cancelled | Completed | Partial Pass | Passed | Pending | Re-inspection Required | Re-inspection Required (with fee) | Requested | Scheduled | Total |
|
|
| (Re)Inspection Done Count: | 476 | 5835 | 1434 | 5644 | 2 | 2792 | 2 | 4 | 1 | 16210 |
2E-Actual End Date
| Inspection Number
| Canceled | Completed
| Partial Pass
| Passed
| Re-inspection Required
| Total
|
|
|
|
|
| (Re)Inspection Done Count:
| 2 | 49 | 78 | 98 | 3 | 238 |
|
|
|
|
2F-Actual End Date
| Inspection Number
| Cancelled
| Completed
| Partial Pass
| Passed
| Re-inspection Required
| Requested
| Total
|
|
|
| (Re)Inspection Done Count:
| 2 | 18 | 1 | 14 | 2 | 1 | 38 |
|
|